The following timeline sets out the key milestones and dates for the Plan development process in 2011.
| Activity | Timing | Who |
| Budget 2011 | 19 May 2011 | Government |
| Initial funding allocations made available to PTEs, schools and community groups | June-July | TEC |
| Discussion of performance information and proposed Plans | June-August 2011 | TEOs, TEC |
| Online submission of PTEs’, Schools and Community Providers’ proposed Plans | From July to August 2011 | PTEs, Schools and Community providers |
| Submission of proposed Plans for ITOs and TEIs | 31 August 2011 | TEIs and ITOs |
| Assessment of proposed Plans | July-October 2011 | TEC |
| TEOs are notified of funding decisions | October-November 2011 | TEC |
| Plan delivery begins | From January 2012 | TEOs |
| Funding for 2012 is paid to TEOs in accordance with funding decisions and conditions | From January 2012 | TEC |
-